Construction Holidays in Quebec 2026

In Quebec, construction holidays are mandatory periods during which the entire construction industry is on vacation. They occur in both summer and winter. These holidays play a crucial role for both workers and businesses. However, under specific conditions, certain types of work may continue to ensure essential services and public safety.

What are the official construction holidays in Quebec, and what are the exceptions?

Statutory Holidays in the Construction Industry

Planning ahead for construction projects in Quebec? It’s essential to know the official construction holidays and statutory days off to avoid delays and ensure compliance with industry regulations.

Construction industry Vacation Periods

The Quebec construction industry observes two mandatory vacation periods, each lasting two weeks:

  • Summer Break: July 19 to August 1, 2026

  • Winter Break: December 20, 2026, to January 2, 2027

Statutory Holidays in Quebec Construction

In addition to the industry-wide vacations, construction workers are entitled to 10 statutory holidays throughout the year, with Christmas and New Year’s Day falling during the Winter Break.

  1. New Year’s Day – January 1, 2026

  2. Good Friday – April 3, 2026

  3. Easter Monday – April 6, 2026

  4. National Patriots' Day (Monday before May 25) – May 18, 2026

  5. Fête nationale du Québec (Saint-Jean-Baptiste Day) – June 24, 2026

  6. Canada Day – Observed on July 3, 2026

  7. Labour Day (First Monday in September) – September 7, 2026

  8. Thanksgiving (Second Monday in October) – October 12, 2026

  9. Remembrance Day – Observed on November 13, 2026

  10. Christmas Day – December 25, 2025

Québec construction holidays calendar, 2026 and 2027
Holiday20272026
Summer shutdownJuly 25 to Aug. 7July 19 to Aug. 1
Winter shutdownDec. 19 to Jan. 1, 2028Dec. 20 to Jan. 2, 2027
New Year's DayFri. Jan. 1Thu. Jan. 1
Good FridayFri. Mar. 26Fri. Apr. 3
Easter MondayMon. Mar. 29Mon. Apr. 6
National Patriots' DayMon. May 24Mon. May 18
Québec's National HolidayThu. June 24Wed. June 24
Canada DayFri. July 2Fri. July 3
Labour DayMon. Sept. 6Mon. Sept. 7
ThanksgivingMon. Oct. 11Mon. Oct. 12
Remembrance DayFri. Nov. 12Fri. Nov. 13
Christmas DaySat. Dec. 25Fri. Dec. 25

Two-week shutdowns run from Sunday 12:01 a.m. to Saturday midnight. Statutory holidays as set by the Commission de la construction du Québec. Some rules vary by sector. Source: CCQ, holiday and vacation dates, checked October 15, 2026.

Why are Construction Holidays important?

These industry-wide breaks allow workers to recharge while ensuring project planning aligns with holiday closures. If you’re scheduling tenant improvement project, an interior renovation or any construction project in Montreal, Laval, the North Shore, or any where in Quebec, it’s important to factor in these dates to avoid delays.

Whether you’re a business owner, contractor, project manager, or construction worker, staying informed about these key dates can help you plan your projects efficiently.

Preview of the Xenofan 2027 planning note

Free · 2-page PDF and Outlook file

Get the 2027 planning note

What the construction holidays change in your schedule, your tender and your budget, with the full-year calendar and a file that adds every date to Outlook or Google Calendar.

Enter your email below to receive it.

We use your email to send the note and, if you agreed, occasional planning notes. Privacy policy.

Construction Holidays Calendar in Quebec for 2026. Statutory holidays and others days that mut be considered for your office renovation projects in Montreal, Laval, and neighborhoods. Calendrier de la construction, Construction Calendar 2026 Quebec

Planning around holidays

Construction Calendar and Approved Work During Holidays

In Quebec, most construction sites pause during the Summer and Winter Breaks. However, to maintain essential infrastructure and ensure public safety, some critical work is still permitted. In sectors such as institutional, commercial, and industrial construction, emergency repairs and maintenance may continue during holidays to prevent significant damages or to address post-disaster situations.

In remote regions like Baie-James or areas north of the 55th parallel, certain projects may proceed without interruption, as local needs and conditions allow.

Essential Trades and Specific Work Exceptions

While construction holidays are observed, specific trades are exempt from these breaks due to the nature of their work. These essential trades continue operating during holiday periods, including:

  • Security system installers

  • Refrigeration technicians for service and maintenance

  • Elevator mechanics for repairs and maintenance

  • Millwrights and other mechanics on similar tasks

  • Fire protection system technicians handling emergency works

Additionally, urgent roadwork may be authorized to ensure the safety and functionality of Quebec’s transportation infrastructure

Construction holidays play a vital role in maintaining both worker well-being and the safety of infrastructure across Quebec. While most construction projects temporarily halt during these periods, specific exceptions allow for urgent works, particularly in response to regional needs. For the most up-to-date guidelines and official regulations, visit the Quebec Construction Commission (CCQ) website.


Commercial project delivery · Québec

An office or branch renovation to plan around the construction holidays?

We build the schedule around site shutdowns and statutory holidays from the start, so your work doesn't stop at the wrong time.

Discuss your project →

Are you—or someone you know—planning an office renovation?

Whether you’re preparing a tenant improvement (TI) or a fit-out project, the most critical step is ensuring your construction budget aligns with your test-fit or proposed layout. Too often, projects move forward on assumptions before costs, scope, and constructibility are fully validated.The next step is just as vital: choosing a construction partner you can trust to deliver on budget, on schedule, and without surprises.

Construction projects are inherently complex and can quickly become stressful without the right leadership. The data is clear:

  • Over 50% of failed projects cite poor communication as the primary cause.

  • More than 90% of construction projects exceed their budgets and schedules.

Your office fit-out or commercial renovation deserves better. You deserve better planning, clear communication, and a predictable experience. Corporate real estate leaders and business executive need support to make their decisions. With a tool such as Forecost, it is possible to enter high level project informations, functional needs, and get a preliminary budget estimate. You get a PDF cost report file ready for review, not in 3 weeks but in less than 15 minutes.

The Xenofan Approach

We help organizations make confident office renovation decisions through expert planning and clear communication—before committing to a lease, a budget, or a contract.

We help you navigate the complexities of construction with three core pillars services:

  • Make Decisions with Confidence: We provide upfront cost estimates and constructibility reviews before you commit.

  • Rely on a Trusted Partner: Benefit from seamless, turn-key design and construction managed with rigor and accountability.

  • Stay in Control: Expert supervision and transparent reporting ensure you remain informed and in command of your resources.

A project done right, without surprises, delivered with value. That’s our promise.

📩 Plan better. Decide faster.

📞 Evaluate your project and move forward with confidence!


Independent cost opinion

A capital project to get approved in 2027?

Get an independent number before the lease is signed, the budget is approved or a contractor is engaged. Our fee is the same whether your project proceeds or not.

Discuss your budget →

References

  • CCQ. Construction Holidays and Vacations. https://www.ccq.org/en/avantages-sociaux/dates-conges-vacances

  • CCQ. Aide-Mémoire, Congés Annuels Obligatoires d’Été, Institutionnel et Commercial, et Industriel (2021-2025).

  • Monkhouse, Peter. “My Project Is Failing, It Is Not My Fault.” Paper presented at PMI® Global Congress 2015—EMEA, London, England. Newtown Square, PA: Project Management Institute, 2015

  • Bent Flyvbjerg and Dan Gardner. How Big Things Get Done: The Surprising Factors That Determine the Fate of Every Project, from Home Renovations to Space Exploration and Everything In Between, 2023.

Précédent
Précédent

Level 3 Schedules and CPM

Suivant
Suivant

Tenant improvement allowances